Client
Location
Contract Value
Project Overview
Ferrycarrig was engaged by Bluescope Steel Limited to execute various civil works, including bulk earthworks, sewer and stormwater piping, and road construction. These activities were integral to facilitating the installation of a new metal coating line (MCL7) at the existing Bluescope Western Sydney Service Centre (WSSC).
The civil scope of works included the following:
- Modifications to existing sewer system
- Modifications to existing stormwater system
- Fire hydrants pipework construction
- Electrical pits and conduits construction
- Erection of retaining wall, including all foundation excavation and backfill works
- Establish piling pads for future building foundation work (bulk earthworks)
- Construction of a new site entrance road access including excavation, preparation and installation of road surface
- Removal of all spoil to a certified disposal depot
Following the successful completion of the initial early works package, Ferrycarrig secured an additional contract. In addition to the aforementioned scope, Ferrycarrig was tasked with the supply, manufacture, delivery, and installation of an HV transformer, as well as the design, supply, manufacture, delivery, and installation of a low voltage switchboard.
These undertakings also supported the implementation of the new metal coating line (MCL7).
The electrical scope of works comprised:
- Supply and installation of new padmount substation No: 95782, including circuit
breaker on the 415V side - Supply and installation of earthing to substation 95782 as specified
- Supply and installation of any additional equipment required by law or by Endeavour Energy to enable energization
- Connection of new substation 95782 into Endeavour Energy’s 11kV network
- Liaise with Endeavour Energy to arrange all power outages, and any additional permits required to complete this work
- Complete and lodge all certification and paperwork as required by Endeavour Energy